Which articles of AIA A201 determine the conditions under which funds can be withheld?

Prepare for the NICET Level 3 Fire Alarm Systems Exam. Access flashcards and multiple-choice questions with detailed explanations. Boost your knowledge and readiness for the exam.

The assertion that articles 9-12 of AIA A201 address the conditions under which funds can be withheld is accurate based on the content of these articles. Within this range, various stipulations regarding payments, retention of funds, and circumstances that may justify withholding payment are addressed.

Article 9 primarily discusses the contractor's payment applications and the criteria under which the owner may decline payment. Following this, Article 10 outlines conditions regarding the owner’s right to withhold payments if certain conditions are not met. Articles 11 and 12 further elaborate on disputes and final payments, reinforcing the owner's ability to manage financial transactions and maintain control over funding based on compliance with the contract terms.

Overall, the clarity and specificity of these articles regarding payment withholdings, the contractor's obligations, and the owner's rights provide a comprehensive understanding essential for managing funds in line with contractual agreements.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy